MRT Line From Quezon City to Bulacan Is Almost Halfway Done

The Department of Transportation released a progress report on the Metro Rail Transit (MRT) Line 7 just this Monday. They announced that as of October 2019, the new MRT line connecting Quezon City to Cubao was 49.22% complete.

DOTr’s report stated that “civil works of the underground/depressed, at-grade, and elevated guideway are in various stages of construction, while civil works of nine of the 14 stations are in full swing. Trackworks installation are also ongoing.”

https://www.facebook.com/DOTrPH/posts/1513897105416087

(These Horror Stories Show The Reality Of Commuting In The Philippines)

It also explained that “the required rolling stock of 108 cars have been completed, and are awaiting shipment pending the availability of the depot/holding area.”

MRT-7 is expected to be completed by 2021. The 22-kilometer line is predicted to shorten travel time between Quezon City and San Jose Del Monte in Bulacan from 2-3 hours to just 35 minutes.